After the electronic document to enter, to facilitate future search andcalculation more convenient. After the completion of the input to thecalculation of the amount of the project according to the differentquota sub-summary, the preparation of the main table, the preparation ofthe main table in the previous calculation of the amount of work basedon a loss, the loss rate is different Not the same, remember that steelpartitions do not wear out.
Carefully study the quota, the calculated amount of work set into abudget, to remember the amount of the budget is calculated by the net,in the calculation of anti-corrosion brush oil to remember the steelpartition is not oil, the general H-beam fire only part Brush the primerdoes not brush the finish, leaving all the parts both brush primer andbrush finish, but the specific depends on the specific requirements ofthe drawings.
more information please view sbssteelstructure.com/how-to-apply-fixed-quotation-budget.html